Micro-Paving of Scheduled City Streets to be conducted the week of July 17th
As part of the City of Auburn 2017 Road Improvement Program the following streets will be Microsurfaced the week of Monday 7/17/17.  Just a reminder that this work is weather dependent and streets not done on the planned day due to weather will be rescheduled for the next day, and this is a two day process.  Residents of the effected streets should make alternative parking arrangements on these days as these streets are not driveable for a period of time following the application.  Please use caution when driving in road construction zones.  Thank you.

Planned Microsurface Streets for tomorrow Saturday 7/22/17:

 

Street


From


To


Treatment


Metcalf Dr


Marry St


South St


First and Finish Coat


N Herman Ave


Jarvis St


Wilber Ave


 Finish Coat



Planned Microsurface Streets for today Friday 7/21/17:

 


Street


From


To


Treatment


N Herman Ave


Tyler Dr


Drummond St


First Coat


Bell Ave Ext.


Kearney Ave


End


First and Finish Coat


Throop Ave


Jarvis St


Wilber Ave


 Finish Coat


Throop Ave


Crescent Ave


Silver Ave


Finish Coat


Throop Ave


Camp St


End


Finish Coat


 

Planned Microsurface Streets for tomorrow Thursday 7/20/17:


Street


From


To


Treatment


Koenig Ct


McIntosh Dr


End


Finish Coat


Throop Ave


Jarvis St


Wilber Ave


 First and Finish Coat


Throop Ave


Crescent Ave


Silver Ave


First and Finish Coat


Throop Ave


Camp St


End


First and Finish Coat





Planned Microsurface Streets for tomorrow Wednesday 7/19/17:


Street


From


To


Treatment



Copley St


Lake Ave


Pulsifer Dr


First and Finish Coat


Koenig Ct


McIntosh Dr


End


 First and Finish Coat


Austin Dr


Murray St Ext


End


 Finish Coat


West Lake Ave


William St


Fort St


First and Finish Coat



Schedule for July 18, 2017:


Street


From


To


Treatment



Van Patten St


W Genesee St


Willard St


 Finish Coat


Grant St


Washington St


End


 Finish Coat


Austin Dr


Murry St Ext


End


 First Layer


North Herman Ave


Tyler Dr


Drummond St


 First Layer


Linn Ave


Highland


End


 Finish Coat


Mill St


Owasco St


End


 Finish Coat


School St


Lincoln St


Grover St


 Finish Coat


 


Schedule for July 17, 2017:

Van Patten Street (from Genesee Street to Willard Street) First Layer

Grant Street (Washington Street to the west end) First Layer

Austin Drive (Murry Street Extention to the end) First Layer

North Herman Avenue (Tyler Drive to Drummond Street) First Layer

Linn Avenue (Highland to the end) Finish Coat

Mill Street (Owasco Street to the end) Finish Coat

School Street (Lincoln Street to Grover Street) Finish Coat



Due to weather conditions Thursday 7/13/2017 some of the planned micro-paving was rescheduled listed below.

All work in this contract is weather dependent and could again be delayed and rescheduled.

 

Friday 7/14/2017        
Street                                            Extent                                               Procedure

Linn Ave                                           Entire                                              Scratch Coat
Wilbur Ave                                       Entire                                              Scratch Coat
Mill St                                                Entire                                              Scratch Coat
School St                                            Entire                                              Scratch Coat
Van Patten St                                   Entire                                               Scratch Coat
Capitol St                                   Cayuga St to No. Seward Ave          Overlay 
Ross St Ext                                 No. Marvine to No. Hunter               Overlay   

 
Saturday 7/15/2017        

Linn Ave                                            Entire                                                   Overlay
Wilbur Ave                                         Entire                                                   Overlay
Mill St                                                 Entire                                                   Overlay
School                                                 Entire                                                   Overlay
Van Patten St                                    Entire                                                   Overlay


For more information contact:

William Lupien, Engineer
City of Auburn, NY
24 South Street
Auburn, New York 13021
P 315-255-4129





 
 
Detail Detail
Memorial City Hall
24 South Street, Auburn, NY 13021
Employee Login
Virtual Towns & Schools Website